Nickel Recovery Process Pond Dredging - WA

UAT delivered a dredging solution for a process pond at a gold mining operation in Western Australia, removing accumulated sediment to improve water movement and overall system performance.

Project Overview

Location: Western Australia
Industry: Industrial
Asset: Process Pond

A lined process pond adjacent to a nickel processing plant had accumulated dense nickel fines from repeated shutdown and overflow events, impacting return water quality and reducing overall pond performance.

Scope

  • Removal of accumulated nickel fines from lined process pond
  • Recovery and transfer of material back into plant operations
  • Traversing dredging operation across pond surface
  • Controlled sediment jetting to mobilise dense settled material
  • Operation without interruption to mill activities
Nickel fines recovery from lined process pond Western Australia

Outcome

  • Recovery of nickel fines back into the processing circuit
  • Improved return water quality to the mill
  • Restored operational pond capacity
  • Maintained continuous plant operation during works
  • No damage to pond liner during dredging operations
Dredging the plastic lined process pond to recover nickel fines

Related Services

Process Pond and Dam Dredging

Sediment, Sludge & Slurry Removal

Related Case Studies

Other Dredging Case Studies

Other Mining Case Studies

Discuss a Similar Project

Speak with our team about a tailored solution for your site conditions, materials, and operational requirements.